Shower tower is often used in industrial waste gas purification treatment organic waste gas treatment, is currently a common waste gas treatment good use of a processing equipment. There are a lot of enterprises after the installation of spray tower use for a period of time there will be some problems, in fact, these problems only need to do their own check can be completely resolved, saving time effort, the next Ding Sheng spray tower manufacturers technicians on the frequent 6 kinds of problems solutions to summarize to you, I hope to bring you help.
First, the use of spray tower in the common 6 kinds of problems solutions
1, nozzle clogging
Reason: the liquid in the tank contains too much dust impurities.
Solution: first check whether the water tank filter plate is cracked, the water pump inlet whether the equipment filter, the bottom of the water pump filter is broken, assuming that the above problems in time to repair replace. Nozzle dismantling methods, first remove the window screws to remove the window plate, people into the tower in the counterclockwise direction to remove the nozzle, turn on the pump (water tank water should be replaced with water) work for two minutes after the closure, then loaded with nozzles according to the clockwise direction.
2, packing blockage
Reason: dust viscous impurities in the exhaust gas adhering to the packing ball appearance, such as paint exhaust, grinding exhaust, organic waste gas, etc..
Solution: We first check whether there are the above reasons, in the spray tower tank with cleaning fluid less detergent, as a brief liquid spray cleaning. Assuming that the filler sticky dust is too much, replace the filler in time take out the filler to clean, clean the filler replace the filler back. Afterwards in the spray tower (refers to the water tank) to participate in the appropriate amount of cleaning fluid a little detergent, regularly organize the floating material in the water tank. If the bottom of the material, please add the suspending agent to use, adhere to the water tank clean water without dust dirt.
3、Defogging layer of water
Reason: in addition to the fog filler is too small perhaps the fan air volume is too large in addition to the fog layer of high short specifications do meet the planning requirements.
Solution: the de-mist layer filler full, perhaps the filler layer (tower) grille plate low, add de-mist layer filler, fan equipment frequency converter to reduce the air volume.
4, filler blowing to a pile
Reason: fan air volume is too large, spray tower planning specifications fan air volume does match the composition.
Solution: remove the window screws to remove the window plate, the filler is paved on top of a layer of grille plate perhaps the fan equipment frequency converter to reduce the wind volume.
5, fan start then closed, the water in the water tank will flow out the benefit of the flow outlets
Reason: the reason is that the gas import export specifications fan air volume planning mismatch, spray tower planning specifications fan mismatch.
Solution: fan equipment frequency converter to reduce the air volume gas import export to change the size, mediate the float valve to control the water level.
6, the spray tower nozzle is water water is very small
Reason: the water pump may rotate, perhaps the water level is too low pumping water composition, nozzle clogging, water pump inlet is clogged other reasons.
Solution: whether the pump is working properly, check whether the water level is too low to pump water, should add water in time.
Second, the spray tower operation notes
1, the adjustment of circulating water: the water supply pump the spray tower to decide, when running a boiler can open a boiler, when two three simultaneous operation in winter, the two pumps will be opened, the mud pump flow should be adjusted according to the flow of the circulating pump, so that it is equal.
2, the amount of dosing in the shower tower dosing pool: when running a boiler, add 2 bags of alkali, add 5 bags of quicklime, such as winter operation of two three, according to the corresponding multiplier to increase the amount of drugs, so on.
3, the spray tower sedimentation tank should be cleaned frequently, one week in summer to clean up once, three days in winter to clean up once.
4, gray water separator sewage, discharge once per shift, to open the sewage valve, until there is clear water excluded.
5, the above rotating parts should be frequently checked, oiling, found faults should be promptly eliminated, so as to ensure the effect of desulfurization of the spray tower.
6, in the upper lower staircase dosing should pay attention to the foot, to have independent security, mutual security consciousness.
7, the work is completed in a timely manner to clean up the health, so that people away the site clear.